Over a 12-month Engineering, Procurement, Fabrication & Installation (EPFI) programme.. LES Energy Services Limited, working with CRISCORE Oilfield Services, successfully completed Phase One of the ERHA FPSO Hose Reel Replacement Project.

Project Milestone | ERHA FPSO Hose Reel Replacement Project

After 12 months of Engineering, Procurement, Fabrication and Installation (EPFI) activities, LES Energy Services Limited, in collaboration with CRISCORE Oilfield Services, has successfully completed Phase One of the ERHA FPSO Hose Reel Replacement Project.

Phase One covered the engineering, procurement, fabrication, installation and commissioning of three hose reel units for Methanol, Fresh Water and Diesel services on the port side of the ERHA FPSO.

New Hose reel 2
New Hose reel 2
Existing Hose reel
Existing Hose reel
New Hose reel
New Hose reel

BENEFIT:
Beyond the successful delivery of the units, the upgraded hose reel system is designed to eliminate manual hose handling during bunkering operations through controlled hose deployment and retrieval. This enhances operational efficiency while reducing the level of manual handling required during Methanol, Fresh Water and Diesel transfer operations.

Phase Two will involve the installation and commissioning of the remaining three starboard hose reel units, completing all six units within the project scope.

The successful completion of Phase One is a reflection of months of detailed engineering, procurement, fabrication, offshore installation and close collaboration across the project team.

Another milestone delivered. Another step towards completing the full project scope.